IRWO: Projects In Progress

irwo logo


A photograph from Sonepat Housing Scheme

Projects In Progress

Asansol

Phase-I work has been completed. In Phase-II scheme, as good response was received for type-I units, the scheme was modified with multi-storied type-I units to meet the demand received and accordingly the plans were got approved from the local authority. Contract has been awarded and the construction of dwelling units is progressing well. As the response from Railway men for multi-storeyed type-I is not good, scheme was re-opened including outsiders from 02-12-2013 to 28-02-2014 for booking of balance dwelling units. Vacancies still exist in multi-storeyed type-I units. The scheme may be reopened for booking after a gap of 6 to 9 months.
Asansol: Project Photographs

Sonepat

Construction of 660 dwelling units has been planned. In eleven towers which have been taken up in Phase-I, roof slabs of all 260 type-II units, 192 type-III units and 106 type–IV units, have been cast. Finishing works are in progress. Expected target date of completion is April, 2014 for Phase-I. Draw of lots for specific unit for Type-II was held on 15-02-2014 and the results have been uploaded on IRWO website. Draw of lots for Type-III and Type-IV has been held on 01-03-2014 and 15-03-2014 respectively and the results have been uploaded on IRWO website. Phase-II scheme was reopened from 21-11-2013 to 18-01-2014 for IRWO members, their blood relations and outsiders for filling up a few vacancies in Type-III and IV DUs resulting from withdrawals. All vacancies have been filled up. Phase-II is expected to be completed by September, 2014.
Sonepat: Project Photographs

Moradabad

112.9 Acre of land was procured. Approval of plans from MDA was received on 30-11-2009. Booking letters have been issued to 92 applicants for different types of dwelling units. Tenders were opened on 18-12-2009 and work awarded. Construction work is in progress on 92 units in Phase-I. Roof slabs have been cast for all 92 units. Finishing and external works are in progress. Expected target date of completion is April, 2014. Phase-II scheme for 105 units was launched from 21-01-2013 to 15-04-2013 and extended upto 17-06-2013. Since response to scheme from Railway men is poor, the scheme was opened to IRWO members, their blood relations and outsiders from 13-09-2013 to 12-11-2013, extended up to 12-12-2013 and further up to 12-02-2014. About 50% vacancies have been filled up with the response received.
Moradabad: Project Photgraphs

Zirakpur(Chandigarh)

A new Contract for the work including Phase-II work has been awarded in August, 2012 after terminating the contract fixed in June, 2010 due to slow progress. Work has been restarted and is progressing in full swing. All 195 roof slabs have been cast in Phase-I. RCC foundation work for all 6 blocks of type-IV units and 11 blocks of type-III units has been completed. Expected target date of completion for Phase-I is Sept. 2014. For Phase-II scheme, 102 roof slabs out of 248 have been cast. Phase-II scheme was reopened for members, their blood relations and outsiders from 21-10-2013 and extended up to 20-02-2014 to fill up the vacancies. All vacancies have been filled up.
Zirakpur: Project Photgraphs

Hyderabad Phase III

Area of land measuring about 1.5-Acre has been procured within Lingampally Phase-I scheme. Plans for 60 units were finalized and approved by GHMC. The scheme had been re-opened from 15-11-2013 to 15-01-2014 for booking of vacant DU’s. Contract for construction which was closed due to stay order of A.P. High Court was revived. RWA has withdrawn its writ petition from A.P. High Court. The work at site was re-commenced and the construction in plot B was done up to final floor level (S+4). Brickwork and other works are in progress. In plot A front portion roof of 2nd floor has been cast and shuttering for columns of 3rd floor is to be erected. Application has been submitted to GHMC for revalidation of building plans. Target date of completion is December, 2014.
Hyderabad Ph III: Project Photographs

Chennai Phase II

11.88 Acre of land was procured in year 2004 and housing scheme was announced. Scheme has been launched and booking letters have been issued to 138 applicants. The revised layout plans have been approved by CMDA and Ambattur Municipality. Unit plans have also been approved by the Municipality. Contract for construction of Chennai Phase-IIA was awarded on 27-12-2011 and Contractor had mobilized to commence the work but a court “stay order” was brought by some local residents and work had to be stopped. The ‘stay order’ was contested. The case was heard by Hon’ble High Court and the stay has been vacated. Contractor was advised to restart the work but as he did not comply with the instruction, the contract was rescinded. Fresh tenders were opened on 25-03-2013 and contract for 140 independent dwelling units for Chennai Phase-IIA has been awarded. The new contractor has signed the Agreement and the foundation work is in progress. Chennai Phase-IIB housing scheme for construction of 161 4-storeyed DU’s would be launched shortly in the balance available land.
Chennai Ph IIA: Project Photographs