IRWO: Projects In Progress

irwo logo


A photograph from Sonepat Housing Scheme

Projects In Progress

Asansol

Phase-I work has been completed. In Phase-II scheme dwelling units have been planned. Contract has been awarded and the construction of dwelling units is progressing well. Vacancies still exist in multistoried type-I units. The scheme is likely to be reopened for booking for Phase-II shortly.
Asansol: Project Photographs

Sonepat


Construction of 660 dwelling units have been completed. Possession letters issued for 475 Dwelling Units and 366 Dwelling units have been handed over. Allotment of covered Car Parking for Type-III & Type-IV has been linked with Dwelling Units No. and same is being allotted once full payment is received from the allottees. As regards covered/open car parking for Type-II, Draw is being conducted to decide about the allotment of covered car parking . Draw for allotment of Dwelling Units under Phases-II shall be made in March , 2015
The estimate for services and completion drawing have been submitted to HUDA for issue of Completion certificate.
The Scheme has been re-opened from 5th August, 2014 to fill up the vacancies.

Sonepat: Project Photographs

Moradabad


Work of Moradabad PH-I Scheme for construction of 92 DUs of different type have been completed and allotment letter for Phase-I allottees are under issue

There are few vacancies in Ph-I which are being filled from the allotees of Phase-II after asking thier option for allotment of these DUs.

Work of Moradabad Ph-II Scheme for construction of 81 Dwelling Units of Type I, Type II, Type III, Type IV and Type IV-A has commenced at site and the revised cost is being worked out and shall be informed to allottees shortly.

Moradabad: Project Photgraphs

Zirakpur(Chandigarh)

Structural works up to top roof level of Type-II, Type-III & Type IV for Phase-I and Phase-II have been completed. Finishing works of Phase-I are near completion stage and the works including external services like laying of sewer line water supply line, drainage, roads,electrification work and lifts are likely to be completed by march, 2015.

As regards Phase-II finishing works of all Blocks including external services are progressing well and are likely to be completed in all respects by Oct 2015

Construction of community centre and EWS houses are also in progress

Option for floor preference in being asked from the allottees of Phase-I for Draw purposes which may take place in the month of April ,2015

There are still few vacancies lying in Type-III DUs for which the Scheme has been re-opened w.e.f 6.1.2015

Zirakpur: Project Photgraphs

Hyderabad Phase III

Additional 1.5-Acre land in Lingampally Phase-I was procured from APIIC. Plans submitted to the authorities were approved and tenders were finalized. Preliminary works were taken up at site when Phase-I allottees brought a “stay order” which has since been got vacated. Phase-I allottees filed application in writ appeal in Division Bench of A.P. High Court for staying the construction which has also been dismissed. Contractor has remobilized and construction work has been recommenced. In Plot A, basement with front portion roof up to 8th floor and rear portion up to 5th floor has been cast. All four floors in Plot B have been cast and brickwork and other works are in progress.
Hyderabad Ph III: Project Photographs

Chennai Phase II

Plans for construction of houses have been approved by CMDA. Ambattur Municipality has sanctioned individual plans of the dwelling units. Tenders were invited and technical bids opened on 20-09-2011 and finalized. Contractor was mobilizing to start the work when a writ petition was filed by local residents and work had to be stopped. The writ petition has been dismissed by the Hon’ble High Court and stay vacated. New tender was finalized and work was progressing slowly. The contract has been terminated and fresh tender has been called.
Chennai Ph IIA: Project Photographs

 

 

© 2015 IRWO |