IRWO: Projects In Progress

irwo logo


A photograph from Chennai Housing Scheme

Projects In Progress

Moradabad Ph-II


In Moradabad, 12.9 Acres of land has been procured and construction of dwelling units has been planned in two phases. In Phase-I, construction of all the 92 units has been completed. Draw for allotment of specific unit was held on 29/11/2014 and 09/04/2015. 90 possession letters have been issued and 86 allottees have taken possession.


For Ph-II, 81 dwelling units have been planned. The contract was awarded and the construction work has been completed. Draw for allotment of specific unit was held on 22-10-2016, result has been posted on IRWO website. Allotment letters have been issued. Handing over of units has been started. 22 possession letters have been issued and 6 units have been handed over.

KOTA Ph-I

IRWO has purchased 12.86-Acre of land at Kota and project is planned in two phases. These are single-storied plotted row houses. In Phase-I, 62 dwelling units were planned. The contract was awarded in April, 2015 and the work was hampered due to slow progress by the contractor. Foundation work in 3 blocks was in progress, 33 roof slabs were cast. Contract had to be terminated on 07-09-2016 due to tardy progress of work. Fresh contract has been awarded and Contractor has mobilized at site and started casting boundary wall foundations. Registration of Plots OCF-1 and OCF-2 for dispensary, community centre, etc has been done. The scheme has been re-opened to blood relations of IRWO members, employees of Nationalized Banks, employees of other Government establishments etc. for booking from 08-07-2016 onwards to fill up the vacancies. .

Please click here to download the revised Unit Plan for Type IV (4 BR). Please replace Page 19 of the Brochure with the Revised Plan.

JAIPUR PH-III

A plot of land measuring 3.24-Acre in Sector 37 of Jagatpura in Jaipur, approved by Jaipur Development Authority (JDA) for “residential use” has been purchased and registered in favour of IRWO on 03-12-2013. Building plans have been sanctioned by JDA. 261 multi-storied dwelling units are to be constructed. Tender was opened on 05-08-2015 and work awarded on 27-11-2015. Construction of foundations and stilt roof of blocks A, B, C, D, E and F has been completed. Casting of 4th floor for blocks A, B, C, D and F has been done. Casting of 5th floor for blocks A, D and F has been done. Construction of boundary wall is also in progress. The scheme has been re-opened for blood relations of IRWO members, employees of Nationalized Banks, employees of the other Government establishments etc. also from 08-07-2016 onwards to fill up the vacancies. .
Jaipur Ph- III: Project Photographs

MORADABAD-PHASE-III

Thirty one applications were received in the demand survey for single-storey row houses at Moradabad, closed on 31-12-2015. A turnkey tender including transfer of land, for the construction of 65 single-storey houses was opened on 17-03-2016. Land offered by the tenderers was inspected by the Land Committee on 27-04-2016. Negotiation was held on 15-06-2016. LOI issued on 28-06-2016 was accepted by the Contractor and turnkey agreement has been executed. Transfer, registration and mutation of about 1.9 Ha of land has been done in favour of IRWO. Building plans are under finalisation for submission to Moradabad Development Authority (MDA) for approval.
Moradabad-PH-II: Project Photgraphs .

Chennai Phase II

11.88 Acre of land was procured in the year 2004 and the housing scheme has been planned in two phases. In Phase-IIA, 140 dwelling units have been planned. The contracts were earlier awarded on two occasions but due to various reasons and court cases, the contractors could not complete the work and contracts had to be terminated. Fresh tender has been awarded in first week of June, 2015 and the work is progressing. Scheme has been reopened for booking from 10-11-2016 to 30-12-2016 to fill up vacancies.
In Phase-IIB, 161 dwelling units have been planned. Building plans were submitted to Chennai Metropolitan Development Authority (CMDA) in the month of May, 2015. A number of meetings and discussions were held with CMDA authorities for early approval of plans. In this regard, Member Staff had also written a letter to Chief Secretary, Tamil Nadu Government for early approval of the plans. Building plans for 161 DU’s have been sanctioned by CMDA and Municipal Authorities. Tender for the work has been invited to be opened on 11-01-2017. .

Chennai Ph IIA: Project Photographs

 

Jabalpur

11.88 Acre of land was procured in the year 2004 and the housing scheme has been planned in two phases. In Phase-IIA, 140 dwelling units have been planned. The contracts were earlier awarded on two occasions but due to various reasons and court cases, the contractors could not complete the work and contracts had to be terminated. Fresh tender has been awarded in first week of June, 2015 and the work is progressing satisfactorily. Scheme was reopened for booking from 10-11-2016 to 30-12-2016 to fill up vacancies. Good response has been received.

In Phase-IIB, 161 dwelling units have been planned. Building plans were submitted to Chennai Metropolitan Development Authority (CMDA) in the month of May, 2015. A number of meetings and discussions were held with CMDA authorities for early approval of plans. In this regard, Member Staff had also written a letter to Chief Secretary, Tamil Nadu Government for early approval of the plans. Building plans for 161 DU’s have been sanctioned by CMDA and Municipal Authorities. Tender for the work has been opened on 11-01-2017 and is under process for finalisation. .